2026-11-02 · 08:00–09:30
Camera / sound / data checkout
Rental prep room
Charts, timecode, media labels, backup verification and editorial sample receipt.
Try a production change. Save a draft, notify departments, or ask for approval.
PLAN / PREP TO SHOOT
Rehearsals, fittings, scouts and delivery dates live beside the shoot days they support.
Nov 1 · 18:00 · Rev 02
Fitting moved to 13:00 in the wardrobe room so both performers can finish rehearsal first.
Rev 01 placed the costume / sound fitting at 12:00 in Studio B.
Costume and sound confirm the room; casting informs the performer; transport updates the pickup; AD checks for rehearsal conflicts.
2026-11-02 · 08:00–09:30
Rental prep room
Charts, timecode, media labels, backup verification and editorial sample receipt.
2026-11-02 · 10:00–11:30
Keeper’s cottage
Nina Hart and Casey Vale. Kitchen exchange and key handover. Closed rehearsal; no costume fitting during this window.
2026-11-02 · 13:00–14:00
Changed in Rev 02Wardrobe room
Casey Vale / Ellie: jacket lining test, lavalier position and continuity stills. Transport pickup 12:40 at cottage.
2026-11-02 · 15:00–16:00
Keeper’s cottage
Window test, floor plan, cable paths and access. Proposed lighting addition requires producer approval.
2026-11-02 · 16:15–16:45
Stage B
Coordinator reviews the landing, scenic clearances and Scene 6 clean plate requirements before the stage is released for use.
2026-11-02 · 17:00–17:45
Production office
All department leads report outstanding items. Confirm Day 1 call sheet, location map, meals and transport distribution.
Tue, Nov 3 · 07:00
Control room and kitchen interiors. Controlled window light; quiet dialogue.
Wed, Nov 4 · 06:00
Arrival, coast path and morning departure. All exterior work subject to the location and safety team’s assessment.
Thu, Nov 5 · 12:00
Stair landing and lantern room at dusk/night. Window replacement plates and controlled light effect.
Nov 6 · 10:00
Camera and sound reports, look reference, media verification and VFX plate notes